Phase 10 Risk Closeout Addendum — 2026-07-18¶
This addendum updates the Phase 10 disposition of risks whose state in RISK_REGISTER.md predates the final managed closeout evidence. It does not delete or weaken the canonical risk register.
Resolved or materially reduced Phase 10 infrastructure risks¶
R-077 — wrong Supabase project / protected credential exposure¶
Prior state: blocked until verified access.
Phase 10 closeout state: controlled for the managed development/staging boundary.
Evidence:
- immutable project ref
aeeuscifrxcjmnswqwnqwas verified before managed actions; - 37 migration-ledger entries and all 13 DIREKT application schemas were inspected;
- four required private Storage buckets were verified;
- managed restore run
29641165494passed; - no unrelated Supabase project was substituted;
- protected values remained backend/workflow-only and sanitized evidence was recorded.
Residual risk moves to later production key rotation, access governance and incident monitoring rather than Phase 10 activation.
Cloud Run deployment/recovery drift¶
Phase 10 closeout discovered that rollback recovery restored traffic to a named revision, which pinned future traffic and caused later healthy revisions to become Retired rather than active latest revisions.
Control added:
- recovery now uses
gcloud run services update-traffic --to-latest; - independent staging inspection requires latest-created/latest-ready revision integrity;
- final exact-source chain passed on
5d9313333c49d6501944e6ddba4cd408c540ff47: - deploy
29647717734; - inspection
29647798494; - managed operations
29647821458.
Residual risk is controlled by retaining independent inspection after deployments and the permanent recovery workflow.
Managed restore operability¶
The closeout also corrected native-libpq connection compatibility, btree_gist restore prerequisites and restored-API build ordering. Managed restore run 29641165494 then passed clean restore, integrity, migration-ledger, forward-migration and API-readiness checks.
Risks explicitly carried into Phase 11 entry¶
The following categories remain open or entry-gated and must not be interpreted as resolved by Phase 10 completion:
- R-004 field-agent collusion/bribery — representative operational controls and pilot evidence;
- R-010 verification economics — real operating-cost and willingness-to-pay evidence;
- R-013 legal interpretation — qualified Zambia legal findings;
- R-014/R-048 map/provider suitability — approved provider, quotas, costs and fallback validation;
- R-015 Android fragmentation — representative device/connectivity matrix;
- R-021 research bias — primary controlled-pilot validation;
- R-022 registry access — written permission/terms before any integration;
- R-023 participant-data handling — approved consent/minimization/private storage procedures;
- R-030 production OTP/abuse cost — approved provider and monitored vendor controls;
- R-037/R-058/R-075 fairness/independence/anti-collusion — representative pilot validation;
- R-062 consent/privacy interpretation — approved pilot copy and qualified review;
- R-066/R-074 queue and reconciliation service levels — named ownership, staffing and escalation exercises;
- R-067 secure Android local retention — approved encrypted storage before sensitive real data;
- R-068 production communications — approved provider, consent-at-send, opt-out, idempotency and audit controls.
Stop-gate rule¶
A Phase 11 agent must use this addendum together with RISK_REGISTER.md, docs/phase11/HANDOFF_FROM_PHASE10.md and docs/phase10/PHASE10_CLOSEOUT_2026-07-18.md.
No risk marked for pilot/legal/provider validation may be bypassed merely because Phase 10 infrastructure is green. Unapproved adapters remain disabled and production/public release remains a Phase 12 decision.